School Board approves althletic complex improvements
Archive of construction and facility planning updates


Construction Progress Report


back to top

October 2009

New High School Theater Addidtion

Work Completed and in progress:

  • Working on forming the footings, tying reinforcing steel, pouring footings and walls
  • Site grading, digging footings and installing storm sewers
  • Laying block and brick veneer on all walls
  • Working on roughing in bathroom plumbing
  • Cedar Valley Steel setting steel framing, decking and joists
  • Roughing in conduit and boxes
  • Installing geo-thermal loops
  • Testing concrete and compaction
  • Schedule is about 30 working days behind because of footing problems and over excavation.

Sports Complex

Work completed and in progress:

  • Working on site grading and seeding area west of complex
  • Working on the concession stands and punch list items
  • Washed down the home and visitor bleachers
  • Working on score board
  • Working on a camera system
  • Completed the fence around the sports complex
  • Completed the seeding for the complex site
  • Substantial completion was signed August 24, 2009.

New High School

Work completed and in progress:

  • Working on site grading southwest corner of property
  • Working on punch list for the interior items
  • Training staff on HVAC systems
  • Installing fume hoods in classrooms
  • Completed all of the duct work
  • Working on raising and turning fire hydrants


back to top

September 2009

North Bend Elementary

Work completed and in progress:

  • Installed 4 sub-drain line between side walk and the play ground
  • Installed silt fence around play field that will be re-graded

Sports Complex

Work Completed and in progress:

  • Working on site grading
  • Working on the concession stand and punch list items
  • Washed down the home bleachers
  • Completed the installation of the score board
  • Completed the testing of the speakers and equipment
  • Completed the fence around the sports complex
  • Completed the seeding for the complex site

Substantial completion was signed August 24, 2009

 

New High School Theater Addidtion

Work Completed and in progress:

  • Working on forming the footings, tying reinforcing steel, pouring the house footings and walls
  • Site grading, digging footings and installing storm sewers
  • Laying block on house walls
  • Working on roughing in plumbing
  • Setting steel framing and joists
  • Roughing in conduit and boxes
  • Testing concrete and compaction


back to top

July 2009

Sports Complex

Work completed and in progress:

  • Working on site grading
  • Working score board, and concession stand
  • Completed all the drainage piping
  • Completed testing of the lights and concession stand wiring
  • Completed the installation of the footings for the bleacher contractor
  • Completed laying the turf on the football field
  • Completed the installation of the bleachers and set the press box
  • Running track red rubber has been installed and waiting to paint the striping
  • Installing the plumbing in the concession stand
  • Completed the installation of the score board
  • Completed the installation of the speakers and equipment
  • Installing fence around the sports complex
  • Working on seeding practice fields and surrounding areas

New HS Auditorium building

Work completed and in progress:

  • Working on forming the footings, tying reinforcing steel, and pouring the house footings
  • Site grading, digging footings and installing storm sewers
  • Testing concrete and compaction
  • Project is about 30 working days behind because of footing problems and over excavation

New HS Auditorium building

Work completed and in progress:

  • Working on site grading and bile-swales
  • Completed all of the duct work
  • Working on repairing the terrazzo and installing terrazzo in the east and west corridors
  • The kitchen contractor has completed installing equipment
  • Started the air handler units as per the schedule and some training has been completed
  • MLC and Subcontractors all have been working on punch list and change order items


back to top
June 2009

Sports Complex

Work Completed

  • Working on site grading
  • Working on curbing for the D areas, score board footings, and concession stand roof
  • Completed the masonry block work on the concession stand and restrooms
  • Completed all the drainage piping for the site
  • Completed setting light poles and lights
  • Completed the laser grading on the football field and installing footings for the bleacher
    contractor
  • Completed laying the turf on the football field
  • Installed the visitor side bleachers and will start the home side next week.

Press box will be delivered the week of the July 13th
Running track will start the week of July 8th

 

New HS Auditorium building

Work completed and in progress:

  • Working on forming the footing, tying reinforcing steel, and pouring for the pit
  • Completed the geo-piers
  • Site grading and digging the pit
  • Laying out control points and rough grade stakes
  • Project is about 30 working days behind because of footing problems and over excavation

New High School

Work completed and in progress:

  • Started working on site grading and bile-swales
  • Working on punch list for the interior painting items
  • Working on cleaning up the building, working on punch list items, and ITC items
  • Working on punch list items for electrical items
  • Johnson Controls training CCA staff
  • Completed 98% of the duct work and working on punch list items
  • Repair terrazzo and work on the east west corridors.
  • Completed the epoxy flooring in the building
  • Gym equipment completed installation
  • Kitchen contractor has completed installing equipment
  • Working on piping in the bile-swales
  • Started the air handler units as per the schedule and started some training completed
  • Completed the colored sidewalk at the main entrance and the fire lane in the back


back to top
May 2009

Sports Complex

Contractors on site:

  • MLC Contractors 2-15 People.
    Neuzil Construction 2-8 People.
    Advanced Electrical Ser. Inc. 2-5 People.
    Steve Moyle Masonry 4-8 People.
    Quad City Geo-Thermal 6 People.
    Maxwell Construction 2-6 People.
    MBA Concrete Inc. 2-4 People.
    Mid-West Turf 2-6 People.

Work Completed:

  • Neuzil Construction has been working on site digging footing and site grading.
  • MLC has been working on shop drawing submittals and has started footings for the concession stand.
  • Steve Moyle has completed the masonry block work on the concession stand and restrooms.
  • Maxwell Construction has completed all the drainage piping for the site.
    Advance Electrical has completed setting light poles and lights. Working on score board electrical and underground conduit.
  • MBA has completed the laser grading on the football field.
  • Mid-West has been on site checking subgrade on the football field.
  • MLC has unloaded roof truss and decking for the concession stand and restrooms.


Construction progress meetings have resumed and will be held every other Tuesday at 10:00 am. A new schedule has been submitted.

 

New HS Auditorium building

Work Completed:

  • Contractor is moving in setting up, unloading materials, and concrete removals
  • Working on geo-piers
  • Reviewing geo-pier installation
  • Site grading and back dirt removal underway
  • Laying out control points and rough grade stakes for contractor

Klienman is about 30 working days behind because of footing problems and over excavation.

 

New High School

Work Completed:

  • Started working on site grading
  • Completed 98% of the interior painting
  • Working on casework, door frames, cleaning up the building, installing the mill work in the classrooms, the office areas and laboratories
  • Installing electrical boxes, conduit for the mechanical equipment, classroom lighting and installing parking lot light poles
  • Installing natural gas line connections in the mechanical room, hooking up air handlers, running waterlines, testing lines and setting bathroom and lab fixtures.
  • Completed all of the fire protection
  • Completed the siding, flashing and down spouts around the building
  • Working on getting the exterior glass installed and the exterior doors set
  • Completed 98% of the duct work
  • Completed installing terrazzo flooring.
  • Installing vct in the classrooms and carpet in the offices
  • Completed the epoxy flooring in the building
  • Gym floor has been installed, painted and sealed
  • Gym Equipment has completed their installation.
  • Kitchen contractor has completed installing equipment
  • The school system has cleaned and sealed the common area floor
  • Started the air handler units as per the schedule. They started pumping glycol into the system March 23rd. There has been some training completed.
  • Completed the colored sidewalk at the main entrance. Still have some drives to complete in the back

The schedule is still behind but MLC is meeting the dates that was given to the school board.

 


back to top
March 2009

New High School building

Work completed and in progress:

  • Started working on site grading
  • Completed 95% of the interior painting
  • Working on show cases, door frames, cleaning up the building, installing the mill work in the classrooms, the office areas and laboratories
  • Installing electric switch gear, installing electrical boxes, conduit for the mechanical equipment, classroom lighting and installing parking lot light pole bases
  • Installing geo-thermal lines though out the building, working on natural gas line connections in the mechanical room, hooking up air handlers, running waterlines, testing lines and setting bathroom and lab fixtures.
  • Completed the exterior veneer walls and has completed the interior walls
  • Completed 95% of the fire protection and installing sprinkler heads
  • Working on siding, flashing and down spouts around the building
  • Completed the dry walling the class rooms, corridors and offices
  • Working on getting the exterior glass installed and the exterior doors set.
  • Working on flushing, testing geo-loops, hooking up the headers and installing clygo
  • Completed 90% of the duct work installed and testing the duct
  • Completed installing terrazzo flooring.
  • Installing vct in the classrooms and carpet in the offices
  • Completed the epoxy flooring in the building
  • Completed the gym equipment installation
  • Gym floor has been installed, painted and sealed
  • Kitchen contractor has been unloading equipment and installing as they uncrate it
  • Installing counter tops and interior doors.
  • Started some of the air handler units as per the schedule.
  • Started the sidewalk paving March 23rd

The schedule is still behind but MLC is meeting the dates that was given to the school board.

 

Athletic Complex

Work completed and in progress:

  • Working on site digging footing and getting ready to star grading
  • Working on shop drawing submittals and has started footings for the concession stand
  • Stock piling materials
  • Unloaded some storm drain pipe, will start sub drain piping
  • Working on submittals and underground conduit
  • Rolled back the first two headers as requested

 

North Bend Elementary

Work completed and in progress:

  • Working on doors and the last of the punch list items
  • Exterior work will resume as the weather permits

 



back to top
February 2009

New High School building

Work completed and in progress:

  • Completed 85% of the interior painting
  • Working on show case, door frames, cleaning up the building, installing the mill work in the classrooms and the office areas
  • Installing electric switch gear and installing electrical boxes, conduit for the mechanical equipment and classroom lighting
  • Installing roof drain lines, installing geo-thermal lines though out the building  
  • Working on natural gas line connections in the mechanical room and hooking up air handlers
  • Completed 95% of the exterior veneer walls and completed 98% of the interior walls
  • Completed 95% of the fire protection and installing sprinkler heads
  • Working on siding, flashing and down spouts around the building
  • Completed 95% of the dry walling the class rooms, corridors and office
  • Working on getting the exterior glass installed and the exterior doors set.
  • Working on flushing, testing geo-thermal loops and hooking up the headers
  • Completed 90% of the duct work installed and testing the duct
  • Completed installing terrazzo flooring in the corridors both 1st and 2nd floors
  • Installing VCT in the classrooms
  • Completed the epoxy flooring in the building
  • Completed the gym equipment installation

 

Athletic Complex

Work completed and in progress:

  • Working on shop drawing submittals
  • Stock piling materials and storm drain pipe delivered.

 

North Bend Elementary

Work completed and in progress:

  • Working on doors and the last of the punch list items
  • Working on geothermal heating system control and replaced the energy recovery wheel

 

 


Construction Progress Report


back to top
January 2009

New High School building

Work completed and in progress:

  • Completed 75% of the interior painting
  • Working on show case, door frames, cleaning up the building, installing the mill work
  • Installing electric switch gear and electrical boxes and conduit for mechanical equipment
  • Installing roof drain lines and geo-thermal lines though out the building
  • Working on natural gas line connections in the mechanical room
  • Completed 95% of the exterior veneer walls and has completed 98% of the interior walls.
  • Completed 90% of the fire protection and installing sprinkler heads.
  • Working on siding, flashing and down spouts around the building
  • Dry walling the class rooms and corridors
  • Working on getting the exterior glass installed and the exterior doors set.
  • Working on geo-thermal loops and header and flushing loops and testing loops
  • Completed 85% of the duct work installation
  • Installing terrazzo flooring in the corridors both 1st and 2nd floors and installing VCT in the classrooms
  • The schedule is still behind but everybody has crewed up to meet the dates that MLC completion dates.

 

North Bend Elementary

Work completed and in progress:

  • Working on doors and the last of the punch list items
  • Working on the PA and Fire Protection system
  • Working on getting the building HVAC system under control and programming has been completed

 


Construction Progress Report


back to top
December 2008

New High School building

Work completed:

  • Working on site grading until the ground froze
  • Completed 60% of the interior painting
  • Working on show case, door frames, cleaning up the building, getting ready for mill work and flooring
  • Installing electric switch gear and electrical boxes and conduit for mechanical equipment
  • Installing roof drain lines and geo-thermal lines throughout the building
  • Working on natural gas line connections in the mechanical room
  • Completed 95% of the exterior veneer walls and has completed 90% of the interior walls
  • Completed most of the fire protection and testing the system
  • Installing flashing and down spouts around the building
  • Most of the classroom, offices and labs are dry walled
  • Working on getting the exterior glass installed and the exterior doors set
  • Completed 75% of the duct work installation

Mike Hahn and Dallas Norman of MLC attended the December, 2008 School Board Meeting and went over the projected schedule. Mike Hahn has asked for a time extension due to the weather.

 

North Bend building

Work completed:

  • Worked on the last of the punch list items
  • Working on the PA and Fire Protection system
  • Working on sealing up the entrances and windows
  • Working on heating and programming thermostats and getting a new energy recovery wheel
  • Worked on the media area carpet and glue replacement during the holiday break

 

 


Construction Progress Report


back to top
November 2008

New High School building

Work completed:
  • The building has been enclosed since the first week of the month
  • Working on storm water ponds and placing black dirt in the south section
  • Pouring interior equipment pads, installing wood framing for the roofers and installing doors and door frames for the masonry contractor
  • Installed electrical boxes and conduit for the masons and installing switch gear
  • Plumbing for the masonry walls and installing geo-thermal piping
  • Constructing the glazed block walls and the exterior brick veneer walls
  • Erected miscellaneous steel opening, and stairways Larew Co. has been installing misc. piping and installing their AHU equipment.
  • Installing their duct work in the center section and north section
  • Completed the roofing with some miscellaneous ties to complete
  • Quad-City Geo working on installing the geo thermal field and installing headers.
  • Placed most of the concrete parking area and are working on the frontage roads and the fire lane
  • Most of the metal studs installed and installing drywall in the north section and the office area
  • Installed the metal trim and down spouts around the gym and north section and starting to work on the center section roof flashing
  • Sub-floor installed in the south section
  • South section is mostly painted and working in the class rooms in the north section

The project is still behind about 45 working days because of the bad weather, but can still make up the lost time.

 

Athletic Complex

Work completed in November 2008:
  • Working on sub grade and site grading
  • Working on submittals and misc shop drawing submittals
  • Installing storm, sanitary sewers and water mains
  • Working on the headers and is getting ready to loop them back to the south on the east end

 

North Bend Elementary School

Work completed in November 2008:
  • Finished most of the punch list items
  • Finished cleaning up the exterior for this winter
  • Installing parking lot light bases
  • Poured the side walk to the north
  • Sealing up the entrances
  • Working to get the building geo-thermal controlled
  • Training and testing on the fire protection panels and equipment
  • The exterior signage is yet to be completed

 

Amana Parking Lot

Work completed in November 2008:
  • Finished the grading, cleanup and removed the temporary drive
  • Completed the parking lot paving
  • Finished installing the new parking lot light pole and light
  • Finished the fine grading and seeding
  • Final walk through was Friday October 3, 2009 and the punch list items was completed November 24, 2008

 

 


Construction Progress Report


back to top
October 2008

North Bend Elementary School

Work completed in October 2008:
  • Worked on the last of the punch list items and cleaning up the building
  • Working on the PA system
  • Poured the north side walk
  • Working on sealing up the entrances
  • Exterior punch list items completed
  • Working on programming heating

 

New High School

Work completed in October 2008:
  • Completed 90% of the site grading
  • Pouring all the interior floors
  • Installed electrical boxes, light pole bases and conduit
  • Installing interior water piping in all sections of the building
  • Constructed all of the exterior concrete block walls and has about 70% of the veneer completed.
  • Working on outlet drain pipes for the bile swales
  • Completed all of the structural steel installed
  • Completed 70% of the duct work
  • Will start pulling wire this week
  • Installed 160 geothermal loops and the vault
  • Completed about 70% of the exterior paving
  • Working on getting the bile swales in the parking lot completed

The project is still 45 days behind due to the continued rains this summer.

 

New Athletic Complex

Work completed in October 2008:
  • Working on grading and hauling sub grade materials
  • Working on shop drawings
  • Begun to work on drainage ways and piping
  • Working on sub grade for the football field and should be done this week

 

 

back to top

School Board approves athletic complex improvements

Improvements to the CCA athletic facilities received a boost last month as the board voted to award a contract to construct a new athletic complex west of the exiting football/track stadium in Tiffin. The complex includes an eight-lane track, handicapped accessible parking, home and visitor seating and centralized concession/restroom facilities. A synthetic field will accommodate competition soccer, football and marching band.

This field will also expand physical education opportunities while providing additional practice space for other sports such as baseball, softball & golf. The complex also provides two additional practice fields. The stadium bid was awarded to McComas-Lacina for $4,240,000 and will be funded with revenue from the local option sales tax approved by voters in February of 2007.

Athletic Complex